Experienced professional with a robust understanding of M&E systems across industrial, commercial, and Pharmaceutical sectors. Demonstrates expertise in managing projects from tender to completion, overseeing all aspects of construction, and lead rolls with electrical systems. Proficient in client acquisition, tender costing, procurement, and strategic planning. Skilled in labour management, quality assurance, and maintaining calm under pressure while ensuring effective communication and team building. Career goals include further enhancing leadership capabilities and driving successful project outcomes.
Takes on challenging new role harnessing interpersonal skills, collaboration and problem-solving. Driven to deliver high-quality service and consistent results.
Organised and dependable Construction lead with 26 years of experience. Successful at managing multiple priorities with positive attitude. Willing to take on greater responsibilities to meet team goals.
Overview
11
11
years of professional experience
Work history
Electrical Construction Lead
Fluor Construction
Copenhagen, Capital Region
01.2023 - 06.2026
Joined Fluor in 2023 with the role of Electrical Superintendant overseeing the HVAC BMS systems. progressed works and punch lists.
Progressed into the lead role for the Bus Bar system install and hand over. Worked with the install teams and the client to progress and set up the testing procedure and walk down procedure as nothing was in place for these actions. Produced reports and held client meetings for the works as well as working with the contracts in relation to cost saving.
Lead roll in the electrical field install for lighting / power and production systems in building 45-DSM which included energisation and punch closure of systems and main install items. worked with the construction team and client to progress works and complete tasks.
Coordination of fire alarm system including vesda / inert gas / sprinkler systems to help progress to completion.
Worked with engineering and design on all of the above producing solutions and progressing works to keep the flow going.
Led installation and commissioning of electrical systems ensuring compliance with safety regulations.
Managed project schedules and coordinated with subcontractors to maintain workflow efficiency.
Developed and implemented strategies for troubleshooting electrical issues enhancing system reliability.
Conducted regular inspections and assessments of electrical installations to ensure quality workmanship.
Collaborated with project managers to allocate resources effectively and meet project milestones.
Evaluated electrical designs and specifications recommending improvements for optimal performance.
Optimised work processes by integrating advanced tools and technologies to streamline operations.
Carried out day-to-day duties accurately and efficiently.
Successfully delivered on tasks within tight deadlines.
Demonstrated respect, friendliness and willingness to help wherever needed.
Supported team by demonstrating respect and willingness to help.
Operations Manager
Mirram Special Works Ltd
01.2019 - 01.2021
Led cross-functional teams to streamline operations and enhance overall efficiency.
Developed and implemented strategies to optimise resource allocation and productivity.
Managed relationships with key stakeholders to ensure alignment on operational objectives.
Oversaw daily operations and coordinated with various departments to ensure seamless workflows.
Facilitated training programmes to enhance staff capabilities and foster professional development.
Conducted regular assessments of operational processes to identify areas for improvement.
Implemented quality control measures, enhanced product standards.
Developed risk mitigation strategies, ensured business continuity during crises.
Reduced overhead costs through efficient resource allocation and budget management.
Managed vendor relationships to ensure timely delivery of services.
Directed safety protocols implementation, created safer workplace conditions.
Coordinated cross-functional teams, achieved project milestones on schedule.
Project Manager
Mirram Special Works Ltd
01.2017 - 01.2019
Placed into this role to stream line the business and make headway with new clients and future business. Works involved, the day to day workings of the company. Client liaising, job costing, job design, procurement for works won. Organisation of site labour and contract progress. Also looked after van fleets and contracts for the overheads. The main items of work would be site electrical & mechanical installs including the site temp works. This would vary with the clients we support. From full site set ups (full welfare install / kitchens / drying rooms / office and date / full working site 110v electrical install inclusive of design. CCTV & Security / Fire Alarm / Site water and waste. All of the above works again vary in size, some contracts would be from £10k to some of the bigger works contracted at£700k. The full portfolio I look after would be in the region of £2m inclusive of the social housing re-gen works and facility works also on the books. I also handle the government packages we have inside of the Houses of parliament.
Took up this roll to gain more work and produce a working standard across the business. Works involved where mostly M&E site temporary installs (Main MDU/ Trip install to all the 110v equipment. We also installed all the data and cctv packages for the sites)
Led multiple cross-functional teams to successfully deliver complex projects on time.
Developed comprehensive project plans that defined scope, objectives, and deliverables.
Managed stakeholder communications to ensure alignment and mitigate project risks.
Project Manager
LME Ltd
01.2015 - 01.2017
Worked with a small team of engineers to install electrical works, majority would be new Data Centre installs which would include all the electrical containment and wiring along with the UPS & Generator install works & Bus Bar. Liaised with the main contractor and procured all the materials and installed to working drawings throughout the contracts.
Education
High School Diploma -
Barnfield College Technology
Luton
Skills
Good knowledge of M&E systems in relation to industrial / commercial and housing
Good working knowledge of computer systems for job building and costing, also design
Current role allows me to take jobs from tender process all the way to completion and hand over
Client Acquiring
Tender Costing
Design if required
Management on a day to day bases with the teams allocated to the project
H&S / RAMs write ups and audits if required
Client liaising and progress reporting
Forecasting while projects are active
Better Buying throughout the projects and procuring competitive rates
Labour Management on a daily bases over multiple projects
Final finishing and certifying works once complete
Calm under pressure
Problem-solving
Communication skills
Team building
Strategic planning
Leadership
Resourcefulness
Quality Assurance
References and Contract Values Worked On
Adrian Cook, fluor construction manager. adrian.cook@fluor.com +44 7741 152453
Ben, White, Senior QS, Ben.White@unitedliving.co.uk, 07718637021, United Living, 2020, 2023, M&E Packages for social housing including new electrical and heating system installs £2.5m
Lee, McSweeney, Lee@lmelectrical.co.uk, 07768448755, LME Ltd, 2014, 2016, Data Centre Electrical Installs, Equinix LD4,5,6,7,10,13,MA1 New and refurbishment of data centre electrical fit outs including UPS and Generator installs £1.5m, Digital Realty, Fountain Court, Chessington, Electrical Main Install for the Centre from Transformer sets plus main panel connections and installs, full data centre containment install along with all submain and general power and lighting £1.6m, https://www.lmelectrical.co.uk
Paul, Lyons, Wates Commercial Manager, Paul.Lyons@wates.co.uk, 07876654254, Wates, 2018, 2020, Houses of Parliament, Derby Gate electrical site temps M&E £1.1m